LAPORAN KEMAJUAN KERJA BERKALA BUKAN PAVEMEN 2022 (FASA 2)

 

KERJA MEMBAIKI PEMBENTUNG CMP ROSAK DI LALUAN FT066B SEK 16.700, JALAN SUNGAI SAM – DABONG, KUALA KRAI, KELANTAN.
TARIKH MULA KERJA : 23.04.2022
TARIKH JANGKA SIAP :ON PROGRESS
KOORDINAT : 5.293229, 102.154718
TARIKH LAPORAN : 30.05.2022
1.0) DRAINAGE (40%)
1.1) Precast Reinforcement Concrete HDPE Pipe Culvert (20%): 75%
1.2) Outlet, Head wall and Wingwall (20%):
2.0) SLOPE REPAIR AND SLOPE STABILISATION (30%)
2.1) Rock Fill For Slope Protection (30%) :
3.0) PAVEMENT AND SHOULDER (25%)
3.1) Reconstruction (25%) : 80%
4.0) ROAD FURNITURE(5%)
4.1) Painting of New Markings (5%) :
PERATUS KEMAJUAN KERJA KESELURUHAN (100%) : 35%

Artikel/Berita Terkini

28,531 CALON UPKK 2023 RAIH KEPUTUSAN CEMERLANG 8A

PUTRAJAYA, 18 APRIL: Seramai 28,531 daripada 230,587 calon yang menduduki Ujian Penilaian Kelas KAFA (UPKK) 2023 berjaya mencatatkan keputusan cemerlang …
Maklumat Lanjut

TIPS PENGGUNAAN BARANGAN ELEKTRIK SEMASA DI RUMAH

Barangan elektrik tidak dapat dinafikan sangat banyak membantu memudahkan tugasan domestik seharian. Tugasan memasak, mengemas rumah dan mencuci pakaian tidak …
Maklumat Lanjut

LAPAN ANGGOTA FRU DIDAKWA SIMPAN BAHAGIAN BADAN PELANDUK

Lapan anggota polis dari Unit Simpanan Persekutuan (FRU) dihadapkan ke Mahkamah Sesyen di sini, hari ini, atas pertuduhan menyimpan bahagian …
Maklumat Lanjut